Customer: | Oevermann Verkehrswege GmbH |
Scope of Work: | Concrete paving including Joint Installation |
Construction Time: | 05/2011 + 07/2012 ( Built in 2 Sections) |
Main Deliverable: | 135.000 m² Betoneinbau und Herstellung |
Joints Installation: | 54.000 m Longitudinal Joints, 27.000 m Cross Joints |
Built-in Fitments: | 2 pcs. (ca. 3500 m2) |
The works ware carried out in 2 sections. First was completed direction to Osnabrück in 2011. After completion and opening to traffic, the works began in the opposite direction. The concrete pavement on the second section was completed in July 2012.
The scope of works included concrete pavement installed in two layers, concrete production and joint installation. Batching plant GHS Modulmix was used for mixing of approximately 40,000m3 of fresh concrete. Concrete paving on main carriageway was done with slipform paver Wirtgen SP1500 and with smaller SP500 for paving on slip roads.
Concrete paving of each direction was completed in only 10 days.