Airport construction BER Schönefeld

Customer: Johann Bunte Bauunternehmung GmbH & Co. KG
Scope of Work: Einbau und Herstellung der Betondeckeauf dem BER
Construction Time: 11/2018 – 08/2019 in 2 Bauabschnitten
Joints Installation: ca. 30.000 m² Concrete installation and production
Other: 6500 m³ HGT mischen und verbauen
Equipment: SP1500
Wirtgen SP500
Liebherr Mobilmix 2 x 3,33m³

At BER Airport, the M5 and M6 taxiways of the flight operations areas were renewed.
Key data on the M5 and M6 taxiways

Concrete: 17.580 m3
Concrete area: 30.000 m2
Concrete height: 40 cm
Transverse Apparent Joints: 6.110 m