Customer: | Kemna Bau Andreae GmbH & Co. KG, Hamburg Branch Office |
Scope of Work: | Installation and production of concrete pavement at HH airport |
Construction Time: | 03/2020 - 08/2020 in 2 construction phases |
Joints Installation: | ca. 40.000 m² Concrete installation and production |
Other: | 53.623 kg Bewährungsstahl verbaut |
Equipment: | Wirtgen SP1500 Wirtgen SP500 Liebherr Mobilmix 2 x 2,5m³ |
At BER Airport, the M5 and M6 taxiways of the flight operations areas were renewed.
Key data on the M5 and M6 taxiways
At Hamburg Airport, the flight operations areas in the main field area were renewed. The construction measures carried out had to be coordinated in terms of space and time so that ongoing operations at the airport were not impaired.
Key data on the renewal of the flight operations areas in construction phases 9 and 10:
Concrete: | 17.580 m3 |
Concrete area: | 38.521 m2 |
Concrete height: | 40 cm; 60 cm |
Reinforcement: | 53.623 kg |
Transverse Apparent Joints: | 6.745 m |